Technical analysis completed, including review of any permitting issues, operating cost review, construction concerns
January 2016
Selection Committee meeting (potential shortlist)
January – February 2016
Public information/outreach
February 2016
Public presentations by finalists (Coliseum)
February – March 2016
Public survey period (online)
March 2016
Survey outcome
March 2016
Selection and ranking by Selection Committee
May 2016
City Council approval of ranking by Selection Committee
May - July 2016
Contract Negotiations & Approval
July - August 2016
Present Contract to Council for Approval
August - October 2016
Concept Refinement
Winter 2015
Complete Schematic Design
November 2015
City Council approves Design Team rankings for Pier Approach
February 2016
Select Pier Operator
March 2016
Pier Approach Public Workshop
April 2016
Schematic design report presentation to City Council
Summer 2016
Pier - design development phase complete
Summer 2016
Pier Approach design concepts finalized and schematic design begins
Fall 2016
Pier –construction documents complete
Jan - March 2017
Pier Approach
Commence Design Development Phase
March/April 2017
Pier
Guaranteed Maximum Price Proposal No. 1 from Skanska
Obtain U.S. Army Corps of Engineers Environmental Permit for Pier
Complete 100% Construction Documents of non-marine work
April/May 2017
Pier Approach
Skanska to deliver Design Development phase estimate
Pier
City Council approval of GMP Amendment No. 1 (marine work)
June - August 2017
Pier Approach
Commence Construction Document Phase
Pier
GMP Proposal No. 2 (non-marine work) received from Skanska
City Council approval of GMP Amendment No. 2 (non-marine work)
Sept/Oct 2017
Pier Approach
Obtain final Permits for Pier Approach
GMP Proposal for complete Pier Approach received from Skanska
Pier
Commence construction on balance of Pier
Spring/Summer 2018
Final Guaranteed Maximum Price (GMP) approved
Commence construction on Pier Approach
Doc Fords lease approved
Pier public art selected
Lease with Duke Energy for solar canopy
Education Center lease approved
2nd Restaurant at Pier Head announced
Design development for Doc Fords restaurant, Education Center, Kids Play area and shade structures
Winter 2018-19
Design and construction drawings for all restaurants and cafes
Design and construction drawings underway for Discovery Center, kid’s playground and shade structures
Spring 2019
Final designs complete and foundations begin for public art installations
Construction continues on the Pier Head Building, Discovery Center, Doc Fords and the Pavilion
Marketplace structure delivered and installed
Seawall repair and restoration continues
Exterior furniture contract approved
Summer 2019
Gateway construction begins
Construction continues on the Pier Head Building, Discovery Center, Doc Fords and the Pavilion
Market Stalls delivered and installed
Site preparation for Kids Play equipment
Winter 2019
Interior work on the Pier Head Building, Discovery Center, Doc Fords and the Pavilion
Installation of play equipment
Installation of boardwalk, lighting and landscaping in the Coastal Thicket
Completion of solar panel installation in Pelican parking lot
Public artwork arrives; foundation work completed for artwork
Installation of vendor stalls in Marketplace
Pier Head Construction Progresses
On April 16/17, a massive construction effort took place - the concrete pour for the 4th floor of the Pier Head building. It took 77 cement trucks, 80 workers and eight and a half hours to complete this task. The Pier Head building is taking shape along with other buildings within the Pier District.
Pier Update: December 2016
Pier Update: January 2016
About the Process
Shortly after his election, Mayor Kriseman brought together the various factions from the previous Pier process which resulted in the referendum to stop design on the proposed Lens design. This group of stakeholders worked with the mayor to develop this current process, which was announced on May 1, 2014 at a press conference on the waterfront.
The process, designed to be fair, comprehensive and transparent, began with a Working Group that included leaders from the neighborhoods, local businesses and previous stakeholders in earlier Pier discussions. The Pier Working Group’s goal was to engage and inform the public and provide opportunities for their input. The Working Group submitted a final report which delineated the functions that the new Pier should include.
Following the Working Group’s assessment, the Mayor appointed a six member Selection Committee, which directed the release of an RFP to design teams for a new Pier.
Twenty-nine design firms that responded to the city’s initial RFQ, has been narrowed to eight. Those eight firms will provide their concepts to the city on December 15th. Following a technical review and a public survey, the Selection Committee will then make their recommendation to the Mayor and City Council.